Name
Mine water treatment plant ; Bituminous coal and anthracite coal ; Bituminous coal and anthracite coal ; Underground machine mining ; 0.3~1.2 million t/a ; Middle rich water mining area; NESPS2
Use advice for data set This dataset is derived from the Pollution Source Census Report and contains information on pollution emissions and related products. However, it does not include data on energy or chemical consumption, nor does it provide information on waste or co-product generation. When utilizing this dataset, please supplement the missing data based on actual conditions before use
Technical purpose of product or process 该数据集代表一个煤炭开采过程,具体关注的是烟煤和无烟煤的地下机械开采,年产量在30万至120万吨之间。该过程适用于中等含水量的矿区。所产煤炭适用于多种应用,包括能源生成、冶金工艺以及作为化学合成的原料。
Classification
Class name : Hierarchy level
  • ILCD: Reference Parameters / Energy carriers and technologies / Hard coal based fuels
General comment on data set the Technical of end-of-pipe management technology for pollution arsenicisPhysical treatment,Its Technical efficiency of end-of-pipe management80,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)
Copyright No
Owner of data set
Quantitative reference
Reference flow(s)
Technological representativeness
Technology description including background system the Technical of end-of-pipe management technology for pollution arsenicisPhysical treatment,Its Technical efficiency of end-of-pipe management80,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)
LCI method and allocation
Type of data set Unit process, single operation
Data sources, treatment and representativeness
Deviation from data treatment and extrapolations principles / explanations None
Data source(s) used for this data set
Completeness
Completeness of product model No statement
Validation
Type of review
Dependent internal review
Reviewer name and institution
Data generator
Data set generator / modeller
Publication and ownership
UUID 331a5365-703b-44b4-9311-0ba557138dae
Date of last revision 2024-04-15T22:04:36.322620+08:00
Data set version 00.01.005
Permanent data set URI https://lcadata.tiangong.world/showProcess.xhtml?uuid=331a5365-703b-44b4-9311-0ba557138dae&version=01.00.000&stock=TianGong
Owner of data set
Copyright No
License type Free of charge for all users and uses

Inputs

Type of flow Classification Flow Location Mean amount Resulting amount Minimum amount Maximum amount
Product flow
Materials production / Raw materials 1000.0 kg1000.0 kg
General comment nan

Outputs

Type of flow Classification Flow Location Mean amount Resulting amount Minimum amount Maximum amount
Elementary flow
Emissions / Emissions to water / Emissions to water, unspecified 7.0E-8 kg7.0E-8 kg
General comment the Technical of end-of-pipe management technology for pollution MercuryisPhysical treatment,Its Technical efficiency of end-of-pipe management80,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)
Product flow
Emissions / Other substance type 3.1E-4 kg3.1E-4 kg
General comment the Technical of end-of-pipe management technology for pollution Petroleum-related wasteisPhysical treatment,Its Technical efficiency of end-of-pipe management90,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)
1750.0 1750.0
General comment the treatment technology for the pollution of Waste waterdidn't offered,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)
Elementary flow
Emissions / Emissions to water / Emissions to water, unspecified 0.0145 kg0.0145 kg
General comment the Technical of end-of-pipe management technology for pollution chemical oxygen demandisChemical treatment,Its Technical efficiency of end-of-pipe management90,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)
Elementary flow
Emissions / Emissions to water / Emissions to water, unspecified 1.68E-5 kg1.68E-5 kg
General comment the Technical of end-of-pipe management technology for pollution arsenicisPhysical treatment,Its Technical efficiency of end-of-pipe management80,The formula for calculating the actual operation rate (k-value) of the end-of-pipe treatment facility is k = normal operating time of treatment facilities (days/year) / normal production time of enterprises (days/year)