Key Data Set Information
|
Location
|
CN
|
Name
|
Municipal sludge treatment and disposal;wet sludge moisture content 70%-75%;co-incinerated with garbage to generate electricity
|
Use advice for data set
| When employing this data set for Life Cycle Assessment, ensure that the system boundary is correctly defined as starting from the point of wet sludge with a moisture content of 70%-75%, post mechanical compression and dewatering at the sewage treatment plant, to the end-of-life disposal. Emphasize the co-incineration process with garbage for energy recovery which should be accounted for in the energy balance and emissions calculations. Special attention should be paid to the allocation procedures between waste treatment and energy production when using this data. |
Technical purpose of product or process
| The municipal sludge treatment and disposal process described is primarily utilized for the management of wet sludge, with a moisture content between 70%-75%, originating from sewage treatment plants. The wet sludge is transported within the facility and co-incinerated with garbage to generate electricity. This process is intended for municipal waste management facilities, particularly those which practice co-incineration as a means to both manage waste sludge and produce energy. |
Classification
|
Class name
:
Hierarchy level
|
| This calculation takes a waste incineration treatment plant as an example, which processes 1040 tons of municipal solid waste per day, and the basic moisture content of waste received is 49.38%. |
Copyright
|
No
|
Owner of data set
|
|
Quantitative reference
|
Reference flow(s)
| |
Functional Unit
|
The life cycle study boundary starts from the wet sludge (moisture content is about 70% ~ 75%) after mechanical compression and dewatering in the sewage treatment plant to the final disposal functional unit adopts 1t wet sludge after mechanical compression.
|
Technological representativeness
|
Technology description including background system
| The boiler evaporation capacity is 48t/h, the furnace temperature is 870~1150°C, and the steam turbine generator set is 16.6MW at full load. |